WATER MASTER PLAN
Bringing clean water to our community — for generations to come
View or download the full Water Master Plan PDF (245 pages)
The Water Master Plan includes the following projects. All timeframes are subject to change based on many factors that could affect our sequencing of projects and the need. If you have specific questions about any of these projects, please call our office at 541-354-1818.
CLICK ON PROJECT TITLES TO VIEW / DOWNLOAD A PDF OVERVIEW
Project # | Title | Estimated Cost | Estimated Timeframe |
---|---|---|---|
1 | South Reservoir | $1,651,000 | 2017-2020 |
2 | Dog River to Cooper Spur | $2,401,200 | 2026-2030 |
3 | Cooper Spur-London Drive Creek to Culbertson | $1,566,000 | 2026-2030 |
4 | Culbertson to Cooper Spur | $101,500 | 2017-2020 |
5 | Cooper Spur-Culbertson to Baseline | $1,409,400 | 2026-2030 |
6 | Baseline Drive – West of Tollbridge | $1,957,500 | 2021-2025 |
7 | Allen Road-Baseline to Woodworth | $1,740,000 | 2026-2030 |
8 | Trout Creek Ridge Road | $2,305,500 | 2026-2030 |
9 | Sperry Road Loop | $1,057,900 | 2017-2020 |
10 | Highway 35 Near Hillcrest | $1,479,000 | 2021-2025 |
11 | Neal Creek/Booth Hill Road | $1,500,750 | 2026-2030 |
12 | Hwy 35 and Endow Drive | $435,000 | 2017-2020 |
13 | Booth Hill to Odell | $3,314,700 | 2021-2025 |
14 | Central Vale Dr – Hwy 35 to WyEast | $1,315,875 | 2017-2020 |
15 | WyEast Road – Central Vale to Sylvester | $645,975 | 2017-2020 |
16 | WyEast Road – Sylvester – Sylvester to Lippman | $1,148,400 | 2026-2030 |
17 | Sylvester Road to West Side Reservoir | $1,395,625 | 2017-2020 |
18 | West Side Reservoir | $2,341,000 | 2017-2020 |
19 | Lippman Road | $739,500 | 2026-2030 |
20 | Davis Drive | $756,900 | 2021-2025 |
21 | Stadelman Drive | $887,400 | 2017-2020 |
22 | Lingren Road – Davis to Ehrck Hill | $870,000 | 2026-2030 |
23 | Ehrck Hill to Dethman Ridge | $2,566,500 | 2026-2030 |
24 | Thomsen Road to Fir Mountain | $2,131,500 | 2021-2025 |
25 | Fir Mountain to Pine Grove | $2,202,550 | 2021-2025 |
26 | East Side Road – South | $3,915,000 | 2021-2025 |
27 | Pine Grove to Paasch Drive | $1,914,000 | 2026-2030 |
28 | East Side Road – North | $2,436,000 | 2026-2030 |
29 | Neal Creek – Hwy 35 to Thomsen | $935,250 | 2017-2020 |
30 | Odell Hwy – WyEast to Webb | $609,000 | 2021-2025 |
– | Additional Project List | $943,133 | 2018 |
– | 2017 Capital Outlay Budget | $156,000 | 2017 |
– | Total Project Costs | $48,829,058 | – |